datacenterbacklash.com

An independent, nonpartisan tracker of America's data center fights — the proposals, the politics, and the people on both sides.
By the numbers

The state of the backlash

Data centers have become one of the fastest-moving land-use and energy fights in the country. The figures below come from published polling, industry trackers, and government research — sources are linked on each tile.

Americans who oppose an AI data center in their local area
71%
Value of projects blocked or delayed in Q1 2026 alone
~$130B
75+ projects — Data Center Watch, via NBC News
State data center bills introduced in the first six weeks of 2026
300+
Share of U.S. electricity consumed by data centers in 2023, per DOE — projected 6.7–12% by 2028
4.4%

Note: Data Center Watch, a frequently cited tracker of blocked and delayed projects, has been described in press reports as having AI-industry-adjacent funding; its figures are widely quoted by both sides. Polling of hypothetical local projects may differ from views on specific proposals.

The tracker

Where data centers are being fought

Major contested proposals and policy fights across the U.S., compiled from local and national reporting. Status reflects the most recent reporting we have reviewed (as of August 2, 2026) and can change quickly — follow the linked sources for the latest.

Tucson & Marana, Arizona

Project Blue

In litigation
Beale Infrastructure — widely reported as linked to Amazon/AWS

Tucson's city council unanimously rejected the campus in August 2025 amid concerns over water and energy use in a Colorado River–dependent desert region, and over NDAs shielding the end user's identity. The project moved to nearby Marana, which approved rezoning; opponents gathered roughly double the signatures needed to force a referendum, but the town rejected the petitions in February 2026. Litigation over the petitions was pending as of mid-2026.

Memphis, Tennessee & Southaven, Mississippi

xAI Colossus & Colossus 2

In litigation
xAI

xAI's supercomputer facilities have been powered in part by on-site methane gas turbines, many of which operated without air permits, according to litigation brought by the NAACP and Earthjustice under the Clean Air Act. Residents of the predominantly Black Boxtown neighborhood cite health concerns. The Shelby County Health Department granted permits in July 2025, which opponents appealed; in June 2026 the U.S. Justice Department intervened on xAI's side, citing national security. The facilities have kept operating.

Prince William County, Virginia

PW Digital Gateway

Effectively dead
QTS (Blackstone) & Compass Datacenters — ~2,100 acres beside Manassas National Battlefield

Once slated to be among the world's largest data center corridors (up to ~23 million sq ft), the project unraveled after a circuit court voided its 2023 rezoning on procedural grounds. Compass abandoned its appeal, the county withdrew from defending the lawsuit in April 2026, and QTS dropped its state supreme court appeal that July. More than 100 landowners with purchase contracts were left in limbo, some suing to exit.

Port Washington, Wisconsin

Cloverleaf campus (OpenAI / Oracle "Stargate")

Under construction
Vantage Data Centers, serving OpenAI/Oracle — $458M TIF district approved Nov 2025

The $15 billion megaproject proceeded, but in April 2026 Port Washington voters passed what was widely described as the nation's first anti-data-center referendum — requiring voter approval for future tax-incentive districts over $10 million, by roughly a two-to-one margin. The measure doesn't affect the existing project; business groups have filed a legal challenge to strike it down.

Saline Township, Michigan

OpenAI–Oracle Stargate campus

Under construction
OpenAI / Oracle / Related Digital — ~250 acres in a township of ~2,300 people

The township initially voted the project down; the developer sued, and the township settled and approved it rather than face mounting legal costs — a sequence critics describe as a small town being litigated into acceptance. Construction began in spring 2026. In July 2026 the township approved a tax break roughly nine times smaller than the developer requested.

Richland Parish, Louisiana

Meta "Hyperion"

Under construction
Meta, powered by new Entergy gas plants — investment reported to have grown from ~$10B to ~$50B

State and parish leaders champion the project; the fight is at the Louisiana Public Service Commission over who pays for billions of dollars in new gas generation and whether Meta's commitments are enforceable. An administrative law judge ordered Meta to disclose jobs and power data, which the company contested, and Earthjustice asked regulators to investigate the project's financing structure. Advocates warn of rate impacts on households; supporters point to jobs and investment.

Imperial County, California

Imperial Data Center

Moratorium + lawsuits
Imperial Valley Computer Manufacturing, LLC — would be California's largest at ~950,000 sq ft

County supervisors approved the project in April 2026 without full environmental review, drawing a CEQA lawsuit from the City of Imperial. Facing backlash over Colorado River water (an estimated ~260 million gallons/year) and air quality in a region with high childhood asthma rates, the county reversed course in June with a 45-day data center moratorium — prompting the developer to sue. A countywide referendum effort is underway.

Source: CalMatters
Granbury / Hood County, Texas

Hood County cluster (Project Patriot, Comanche Circle & others)

Contested
Bilateral Energy, Sailfish Investors, Pacifico Energy and others — 8 projects, 7,600+ acres reported

Eight data center projects have targeted this county of about 62,000 people. After Granbury approved a 2,100-acre rezoning in April 2026, residents sued the city alleging open-meetings violations. Two county moratorium attempts failed 3–2, and the county faces developer lawsuits. Concerns center on aquifer strain, the Brazos watershed, noise, and the county's limited zoning power. In July 2026 Gov. Greg Abbott called for a ban on data center development in rural residential areas.

Statewide, Maine

First-in-nation statewide ban (vetoed)

Statewide policy fight
Would have barred large data centers (over 20 MW) until 2027

Maine's legislature passed the country's first statewide ban on large data centers in April 2026, citing electricity rates and grid capacity. Gov. Janet Mills vetoed it days later, and a House override attempt failed by a single vote.

Hanover County, Virginia

Mountain Road Tech Park

Rejected
Tract — ~430 acres

The county board of supervisors denied the project 4–3 in May 2026. Opponents said its projected ~600,000 gallons/day of water use could consume up to 90% of the zone's supply; the developer had offered $15 million for water infrastructure. Noise, rural character, and skepticism about jobs and revenue also featured.

Source: NBC12 / WWBT
East Vincent Township, Pennsylvania

Pennhurst site data center

Rejected
~1.9 million sq ft proposed at the former Pennhurst State School site

Township supervisors unanimously rejected the proposal in May 2026 over scale, water, traffic, and proximity to homes; a court battle is expected. Across Pennsylvania, municipalities have been adopting 180-day moratoriums, and the state House passed a data center "pause" bill alongside Gov. Josh Shapiro's "responsible development" plan.

DeKalb County & statewide, Georgia

Metro Atlanta moratoriums

Moratorium
Various developers — Georgia Power rate impacts loom over the debate

DeKalb County commissioners voted 5–2 in June 2026 to extend a data center moratorium through September 30 while writing setback, noise, water, and energy rules. Athens-Clarke County denied a project and weighed its own pause; Glynn County rejected a moratorium despite pushback. Community groups voiced anger after the 2026 legislative session ended without action on data center bills.

McCormick County, South Carolina

Data center + gas plant proposal

Contested
Developer not publicly named in reporting reviewed

The county planning commission sided with residents in late July 2026, recommending against rezoning ("No rezoning, no data center"), and the county council chair called for a temporary moratorium. Multiple South Carolina counties enacted moratoriums in June 2026 as a statewide siting bill stalled in the legislature.

Trumbull County & central Ohio

Ohio township pushback

Moratoriums
Ohio hosts major AWS, Google, Meta and QTS buildouts

Trumbull County leaders issued a moratorium halting a data center plan, and several central Ohio communities around Columbus and New Albany have adopted their own pauses. Statewide, fights continue over electricity costs — including AEP Ohio's data center tariff — and Gov. Mike DeWine paused new data center tax exemption requests in May 2026.

Indianapolis & statewide, Indiana

East-side Indianapolis project & county wave

Approved
Indiana hosts Google, Meta, Microsoft and AWS projects

An east-side Indianapolis data center won approval in July 2026 despite community opposition, as the city advanced a data center regulation ordinance. Nearly a third of Indiana counties have adopted moratoriums, bans, or restrictions, according to July 2026 reporting.

Eastern Oregon & statewide

Moratorium petition & tax-break rollback

Statewide policy fight
Eastern Oregon hosts one of the country's largest data center clusters

Oregon Rural Action launched a petition campaign — "secrecy, extraction and exploitation" — seeking a moratorium on new eastern Oregon data centers. The state enacted a law affecting data center tax breaks in June 2026, after 2025's POWER Act created a separate rate class so large users pay their share; Gov. Tina Kotek has said Oregon has been a "cheap date" for the industry. An industry group is running pro-data-center ads in Oregon and six other states.

Denver, Colorado

Citywide one-year moratorium

Moratorium
One of the largest U.S. cities to pause the industry

Denver's city council unanimously approved a one-year moratorium on new data center construction in May 2026 while the city develops regulations.

DeSoto County, Florida

County moratorium

Moratorium
The project that sparked the pause was grandfathered in

DeSoto County approved a data center moratorium on July 29, 2026 — though the controversial project that prompted it can still advance under the terms adopted.

Source: WGCU
Warren & Fairfax counties, Virginia

The fight spreads beyond Data Center Alley

Contested
Northern Virginia is the world's largest data center market

Virginia's disputes are spreading past Loudoun and Prince William: Warren County residents near Shenandoah National Park have crowded planning meetings over a Rockland Road industrial/data center proposal, and Fairfax County residents are organizing against infill projects.

Sources: WJLA
The politics

Where politicians stand

Positions are classified from what officials have actually done or said on the record — votes, vetoes, signed laws, executive actions, and direct statements — with a source for each. Many positions are nuanced; "conditional / mixed" covers officials who back data center growth with strings attached (ratepayer protections, disclosure rules, reduced tax breaks). This is not an endorsement or criticism of anyone listed. Positions evolve; check the linked sources.

Supports expansion Conditional / mixed Opposes / restricts

Federal

WhoStanceWhat they've done or saidSource
Donald Trump (R)President Supports expansion Announced the $500B Stargate venture (Jan 2025); signed Executive Order 14318 (July 2025) streamlining federal permitting for large AI data centers and opening federal land; White House launched a voluntary "Ratepayer Protection Pledge" signed by 187 organizations and 23 governors by July 2026. White House · POWER
Jon Husted (R-OH)U.S. Senator Conditional / mixed Leads the Senate Ratepayer Protection Act requiring data centers of 100 MW+ to pay their own generation and transmission costs: "America must build energy infrastructure for AI while protecting families and small businesses from higher electricity bills." Senate release
Gabe Evans (R-CO) & Kathy Castor (D-FL)U.S. Representatives Conditional / mixed Co-lead H.R. 9340, the bipartisan Ratepayer Protection Act, which advanced out of House Energy & Commerce 52–0 in July 2026. House E&C · The Hill
Bernie Sanders (I-VT) & Alexandria Ocasio-Cortez (D-NY)U.S. Senator / Representative Opposes / restricts Introduced the AI Data Center Moratorium Act (March 2026), a federal moratorium on new AI data centers until safeguards exist. Sanders: "We cannot sit back and allow a handful of billionaire Big Tech oligarchs to make decisions that will reshape our economy." Senate release · Axios
Sheldon Whitehouse (D-RI) & John Fetterman (D-PA)U.S. Senators Conditional / mixed Introduced the Clean Cloud Act (S. 1475, April 2025), which would set an EPA emissions performance standard for AI and crypto data centers. Congress.gov
Dave McCormick (R-PA)U.S. Senator Supports expansion Applauded Amazon's $20B Pennsylvania data center investment (June 2025): Pennsylvania's energy resources "make Pennsylvania a perfect base to power America's innovative technological future through data centers like these." Senate release
Suhas Subramanyam (D-VA)U.S. Representative, Loudoun Co. Opposes / restricts "We have too many data centers at this point" (July 2026); supports a state-level moratorium in Virginia. NOTUS
Dina Titus (D-NV)U.S. Representative Conditional / mixed Called on Nevada's governor (July 2026) to freeze state tax abatements for data centers on federal land pending review. Nevada Current

Governors & state leaders

WhoStanceWhat they've done or saidSource
Abigail Spanberger (D-VA)Governor Conditional / mixed Campaigned on making data centers "pay their fair share"; agreed to a first-in-nation data center energy consumption tax ($0.11/kWh, capped at $600M/yr, from July 2026) while keeping the sales-tax exemption; amended cost-shifting bills in ways sponsors said weakened them. American Prospect · Virginia Mercury
Glenn Youngkin (R-VA)Former Governor (through Jan 2026) Supports expansion Vetoed HB 1601 (2025), a bipartisan bill requiring site, water, and noise impact assessments, saying it "limits local discretion and creates unnecessary red tape." Cardinal News
Brian Kemp (R-GA)Governor Supports expansion Vetoed a 2024 bill pausing Georgia's data center sales-tax exemption; the exemption survived the 2026 session after a repeal passed the Senate but died in the House. Data Center Dynamics · Inside Climate News
Greg Abbott (R-TX)Governor Conditional / mixed Signed SB 6 (2025) giving grid operators oversight of large loads; directed regulators in June 2026 to ensure "everyday Texans are not burdened with the costs"; in July 2026 called for banning data center development in rural residential areas; signed the White House ratepayer pledge. Community Impact · Houston Public Media
Katie Hobbs (D-AZ)Governor Conditional / mixed Signed a 3-year pause of Arizona's data center sales-tax exemption (2026–2029), saying it lets the state examine where data centers "provide economic opportunity and where they're not sucking the groundwater"; vetoed a bill that would have weakened referendum rights amid the Project Blue dispute. AZ Capitol Times · AZ Luminaria
Mike DeWine (R-OH)Governor Conditional / mixed Paused new data center tax exemption requests (May 2026) pending legislative review: "Data centers are a critical component to today's technology-driven economy… it is not a data center ban." Governor's office
Josh Shapiro (D-PA)Governor (2026 re-election race) Conditional / mixed Championed Amazon's $20B investment and fast-tracked permitting in 2025, then pivoted in 2026 to a "GRID" plan of standards tying tax breaks to clean-energy and job thresholds: "We need to be selective about the projects that get built here." Spotlight PA · Inside Climate News
Stacy Garrity (R-PA)State Treasurer; 2026 gubernatorial nominee Opposes / restricts Supports a temporary pause for zoning updates, mandatory rather than voluntary rules, and full repeal of the sales-tax exemption: "You can't just jam it down their throats." Spotlight PA
Mikie Sherrill (D-NJ)Governor Conditional / mixed Won in 2025 on utility costs; announced data center "guardrails" (May 2026) — "Not on my watch, not on your backs" — and signed a three-bill package in July 2026 creating a separate ratepayer class for data centers and making them responsible for infrastructure costs. WHYY · NJ.gov
Jeff Landry (R-LA)Governor Supports expansion Championed Meta's Richland Parish campus and its expansion past $50B: "This commitment from Meta puts Louisiana at the center of America's future in artificial intelligence." Opportunity Louisiana
Mike Braun (R-IN)Governor Conditional / mixed Pro-growth but insists projects carry their own costs: "You're going to shoulder 100%, and you're going to ideally put more on if you want to come here and do business"; signed the White House ratepayer pledge. WFYI · 14 News
Tony Evers (D-WI)Governor Supports expansion Jointly announced Microsoft's additional $4B Mount Pleasant investment (Sept 2025) as an economic development win. WEDC
Bill Lee (R-TN)Governor Conditional / mixed Signed the White House ratepayer pledge (July 2026): "Tennessee has shown we can lead the nation in innovation while protecting hardworking families from higher utility bills." Tennessee Lookout
Tina Kotek (D-OR)Governor Conditional / mixed Signed the POWER Act (2025) creating a separate rate class for large energy users; applauded regulators' ~30% rate increase on data centers paired with a residential decrease. OPB · Governor's office
Janet Mills (D-ME)Governor Supports expansion Vetoed the legislature's first-in-nation statewide ban on large data centers (April 2026); the override failed by one vote. Portland Press Herald
J.B. Pritzker (D-IL)Governor Conditional / mixed Paused data center tax incentives effective July 2026 and urged ratepayer protections and water requirements. MultiState
Justin J. Pearson (D-TN)State Representative, Memphis Opposes / restricts Led opposition to xAI's Colossus facility and its gas turbines, calling for their shutdown and alleging Clean Air Act violations; hosted Rep. Ocasio-Cortez's visit to the site. WREG
Louise Lucas (D-VA)State Senator Opposes / restricts Sponsored SB 253 shifting costs to high-load users (passed 2026); publicly pressed the governor to go further: "Governor, read the damn room." Virginia Mercury · American Prospect

Also notable: Georgia's November 2025 Public Service Commission races — widely tied to Georgia Power bills and data center load growth — flipped two seats to Democrats Alicia Johnson and Peter Hubbard (Georgia Recorder). In June 2026 primaries, incumbents who backed data centers lost races in Utah, South Carolina, and Maryland (Christian Science Monitor).

Legislation watch

Key bills and policies

A snapshot of significant federal and state measures, with status as of August 2, 2026.

PendingRatepayer Protection Act (H.R. 9340 / Senate companion) — bipartisan; requires data centers of 100 MW+ to pay their own generation and transmission costs. Advanced out of House Energy & Commerce 52–0 in July 2026. House E&C
PendingAI Data Center Moratorium Act (Sanders / Ocasio-Cortez, March 2026) — federal moratorium on new AI data centers until safeguards exist; considered unlikely to advance. Axios
EnactedExecutive Order 14318 (July 2025) — streamlines federal permitting for AI data centers over 100 MW, opens federal land, and directs financial support programs. White House
EnactedVirginia 2026 package — site assessments for 100 MW+ projects, water-use reporting, cost-shift protections (as amended), and a first-in-nation $0.11/kWh data center energy tax capped at $600M/year; the sales-tax exemption survived. Virginia Mercury
VetoedMaine statewide ban (April 2026) — first-in-nation ban on data centers over 20 MW until 2027; vetoed by Gov. Mills, override failed by one House vote. Maine Morning Star
DiedGeorgia SB 410 — repeal of the data center sales-tax exemption; passed the Senate in March 2026 but died in the House. Other Georgia data center bills also failed. Inside Climate News
EnactedTexas SB 6 (2025) — PUC/ERCOT oversight of loads 75 MW+, transmission fees, and emergency demand-response/disconnection authority. Utility Dive
EnactedOregon POWER Act (2025) — separate rate class so data centers over 20 MW pay their share; regulators later raised data center rates ~30% while trimming residential rates. OPB
EnactedArizona tax-incentive pause (2026) — three-year suspension of the data center sales-tax exemption, July 2026–June 2029. Bloomberg Tax
EnactedNew Jersey three-bill package (July 2026) — separate ratepayer class for data centers, infrastructure cost responsibility, and grid modernization measures. NJ.gov
EnactedTennessee infrastructure law (2026) — data centers of 50 MW+ must fund their electricity infrastructure upgrades; the law also lets facilities self-power with gas turbines under limited oversight. Six other regulation bills failed. Tennessee Lookout
VetoedWater-disclosure bills — California's AB 93 (2025) and a New Jersey disclosure bill (2025) were vetoed; similar bills have been introduced in New York, Oregon, Georgia, Indiana, Illinois, and Utah. E&E News
DiedWisconsin regulation bill — Assembly-passed measure (reporting, water recycling, grid-cost funding) died in the Senate when the session ended in March 2026. Wisconsin Public Radio
News digest

What the press is reporting

Summaries of significant reporting on the data center fight, in our own words, with credit and links to the original outlets. We summarize; the linked outlets own the reporting.

Jul 14, 2026
Fortune / The Conversation

Data centers boost jobs 4% in cities — rural economies barely feel a dent

A Georgia Tech study finds data centers raise employment about 4.1% and wages about 5.5% in urban areas, with negligible effects in rural counties — and retail electricity prices roughly 5% higher after data centers come online. Evidence for both sides of the jobs debate.

Jun 24, 2026
Christian Science Monitor

Voters signal opposition to AI data centers in local primaries

June 2026 primaries saw incumbents who backed data centers defeated: Utah's Senate president lost by more than eight points after championing a hyperscale project, and commissioners in Utah, South Carolina, and Maryland lost to challengers running against data centers.

Jun 22, 2026
Grist / Spotlight PA

America's data center backlash is bipartisan — can it stay that way?

Reports that roughly 70% of Americans oppose AI data centers in their communities (75% of Democrats, 63% of Republicans), with more than 800 opposition groups across 49 states contesting some 1,500 planned facilities — and restrictive moves from governors of both parties.

Jun 12, 2026
PolitiFact

Fact-check: how much have data centers actually raised electricity prices?

PolitiFact rated "Mostly False" a claim that bills near data centers rose "as much as 267%" — that figure describes wholesale price growth near data center clusters, not household bills. It confirms real data-center-driven costs, including a $9.3 billion (174%) rise in PJM capacity costs attributed to data center demand.

Jun 9, 2026
The New York Times

The movement to stop data centers

Reports more than 100 proposed moratoriums or bans across local, county, state, and national levels; polling showing local opposition rising from about 40% in August 2025 to about 70% by May 2026; and a New York statewide ban on large data centers awaiting the governor's signature.

May 18, 2026
Denverite

Data center moratorium gets unanimous approval in Denver

Denver's city council unanimously approved a one-year moratorium on new data center construction while the city writes regulations — one of the largest U.S. cities to pause the industry.

May 13, 2026
Fortune

America's data centers are thirsty. Rural towns are paying the price

Details two incidents of unauthorized water use — about 29 million gallons via an unmetered hookup at a QTS project in Fayette County, Georgia, and roughly 650,000 gallons taken for dust control by a Project Blue contractor in Tucson. Notes U.S. data centers consumed about 17.4 billion gallons in 2023, projected at 38–73 billion by 2028.

Apr 15, 2026
E&E News by Politico

Thirsty data centers fuel local angst over water infrastructure

UC Riverside researchers estimate $10–58 billion in water infrastructure will be needed for AI data centers through 2030. Columbus, Ohio is raising water rates 18% partly due to data center growth, and the piece notes a mismatch between 50–60-year water infrastructure and 15–20-year data center lifespans.

Apr 10, 2026
Canary Media

Data centers are on the ballot in 2026 — and just failed the first test

Port Washington, Wisconsin voters approved, roughly two-to-one, a referendum requiring voter approval before the city grants major tax breaks — a response to the $15 billion OpenAI/Oracle project underway there. In Festus, Missouri, voters ousted every incumbent council member over a $6 billion data center approval.

Feb 5, 2026
Stateline

With electricity bills rising, some states consider new data center laws

At least a dozen states have implemented or are weighing separate, higher electric rate classes for data centers, plus long-term contract commitments and collateral requirements. Includes both legislator concerns and the Data Center Coalition's response.

Dec 16, 2025
Fortune

A grassroots revolt is turning voters in Republican strongholds against the AI data-center boom

Describes organized opposition in Virginia, Indiana, Ohio, and Pennsylvania, with residents citing noise, diesel exhaust, rising energy costs, and public subsidies. Notes data center power demand projected to grow roughly five-fold over the next decade.

Nov 14, 2025
NBC News

State and local opposition to new data centers is gaining steam

Covers a Data Center Watch study finding $98 billion in projects blocked or delayed between late March and June 2025, with organized resistance spanning 53 groups in 17 states — and the industry's response that members are committed to paying their full cost of service.

Nov 8, 2025
Associated Press

Voters' anger at high electricity bills and data centers looms over 2026 midterms

Reports that utilities sought rate increases exceeding $34 billion in the first three quarters of 2025 — roughly double the prior year — and that data centers' growing power demand has become a central affordability issue in states including Georgia, Pennsylvania, Ohio, and Texas.

Voices

From the front lines — and the other side

Direct quotes as they appeared in published reporting, from residents and organizers fighting proposals and from the industry and its supporters. Inclusion is not endorsement; each quote links to the original source and context.

Residents, organizers & local officials
I'm afraid to drink the water, but I still cook with it, and brush my teeth with it. Am I worried about it? Yes.
Beverly Morris, retiree living next to Meta's data center in Newton County, GeorgiaBBC News, July 2025
How am I going to relax with something buzzing at me 24/7?
Helen Messer, resident, Chesapeake, VirginiaNPR, July 2025
Once they're built, there's nothing you can do.
Lee D'Amore, resident, Chesapeake, VirginiaNPR, July 2025
It's never been red versus blue. It's people who live here versus people who want to industrialize where we live.
Elena Schlossberg, Coalition to Protect Prince William County, VirginiaFortune, December 2025
It's like the Gilded Age, part two. Only bigger.
Kerwin Olson, executive director, Citizens Action Coalition, IndianaFortune, December 2025
To increase it by 40 gigawatts is to almost triple our entire grid for one industry.
Julie Bolthouse, Piedmont Environmental Council, on Virginia's buildoutNPR, July 2025
It is my responsibility to create guardrails to protect Tucson from this industry.
Regina Romero, Mayor of Tucson, Arizona, on rejecting Project BlueAZ Luminaria, August 2025
A data center should not be a potential death sentence for a community's health.
Abre' Conner, NAACP Director of Environmental and Climate Justice, on xAI's Memphis-area turbinesSELC, April 2026
The message was heard throughout the county – we will stop data centers!
Patti Stueckler, winning primary challenger, Calvert County, MarylandChristian Science Monitor, June 2026
Industry & supporters
It's inaccurate to draw a clear line between large load customers like data centers coming online and increases in prices.
Lucas Fykes, director of energy policy, Data Center CoalitionStateline, February 2026
Our goal is that by 2030, we'll be putting more water back into the watersheds and communities where we're operating data centres, than we're taking out.
Will Hewes, global lead for water sustainability, Amazon Web ServicesBBC News, July 2025
The data center industry is building out as quickly as they can to meet that growth.
Dan Diorio, VP of state policy, Data Center Coalition; the group says members are committed to paying full cost of serviceNPR, July 2025 · NBC News
This commitment from Meta puts Louisiana at the center of America's future in artificial intelligence.
Jeff Landry, Governor of Louisiana, on Meta's Richland Parish expansionOpportunity Louisiana, July 2026
Context

The numbers behind the fight — and where they're disputed

Many figures in this debate are contested or easily misused. Here's what the research says, with the caveats attached.

Electricity

DOE/Lawrence Berkeley National Laboratory found U.S. data centers consumed about 176 TWh in 2023 — roughly 4.4% of U.S. electricity — projected to reach 6.7–12% by 2028. National average residential electricity prices rose about 42% from 2020–2025, with steeper increases in some regions; PJM capacity costs for 2025–26 rose $9.3 billion (174%), an increase its market monitor largely attributed to data center demand.

Disputed: The widely-quoted "267%" figure refers to wholesale price growth near data center clusters, not household bills (PolitiFact rated one such use "Mostly False"). Projections vary widely, and analysts note utility interconnection queues contain speculative "phantom" load requests that may overstate real demand. The industry disputes drawing "a clear line" between data centers and household price increases; economists confirm real but smaller effects.

Sources: DOE/LBNL · PolitiFact · Stateline

Water

U.S. data centers directly consumed about 17.4 billion gallons in 2023, projected at 38–73 billion gallons by 2028 (LBNL figures); a medium-sized facility uses roughly 110 million gallons a year. UC Riverside researchers estimate $10–58 billion in water and sewer infrastructure will be needed for AI data centers through 2030.

Disputed: Companies point to closed-loop and air cooling and "water positive by 2030" pledges; critics counter that company figures often exclude the indirect water used by power plants and local aquifer effects.

Sources: Fortune · E&E News

Jobs

A July 2026 Georgia Tech study found data centers raise long-run local employment roughly 3.5% overall — about 4.1% in urban counties but a negligible amount in rural ones — with wages up about 5%.

Disputed: Opponents note hyperscale facilities employ few permanent workers ("$3 billion boxes that create maybe 30 jobs," in one organizer's words); the industry counters with thousands of construction jobs and supply-chain effects.

Source: Fortune / The Conversation

Taxes & incentives

Data centers can be enormous local taxpayers — a QTS campus in Fayette County, Georgia is projected to generate $150–200 million in annual tax revenue — which is why many localities court them even amid opposition. At the same time, states including Virginia, Arizona, Ohio, and Illinois moved in 2026 to trim, pause, or offset data center tax breaks.

Disputed: Watchdog groups argue per-job subsidy costs are extreme given small permanent headcounts; industry argues facilities often become a locality's largest taxpayer.

Sources: Fortune · Virginia Mercury

The scale of opposition

Data Center Watch tallied $64 billion in projects blocked or delayed from May 2024–March 2025, $98 billion from late March–June 2025, and roughly $130 billion across 75+ projects in early 2026, with 800+ opposition groups active across 49 states. Gallup found 71% of Americans oppose an AI data center in their local area (March 2026).

Disputed: Data Center Watch has been described in press reports as having AI-industry-adjacent funding, and itself acknowledges that attributing delays "oversimplifies a complex landscape." Opposition to hypothetical nearby projects doesn't always translate to opposition in specific votes.

Sources: Data Center Watch · Gallup · Grist/Spotlight PA

Get in touch

Send a tip — or a correction

Fighting a proposal in your town? Know about a project we're missing? Work in the industry and think we got something wrong? We want to hear from you. If any information on this site is incorrect, please tell us — we take accuracy seriously and will review and correct errors. Submissions can be completely anonymous: no name or contact information is required.

We don't require or collect names. Leaving the email field blank keeps your submission anonymous to us; like any web form, submissions pass through our hosting provider's form service (Netlify), which processes them subject to its own privacy practices. Please don't submit confidential documents you're not authorized to share. Tips are leads for further research, not published as fact.

About

About this site & disclaimers

What this is

datacenterbacklash.com is an independent tracker of the growing public debate over data center construction in the United States. The site's name refers to the phenomenon we cover — the wave of community responses to the data center boom — not to a position we take. We aim to document, evenhandedly, where projects are proposed and contested, what elected officials have done and said, and what credible reporting and research says about the impacts, both claimed benefits and claimed harms.

Independence

This site is not affiliated with, funded by, or coordinated with any political party, campaign, candidate, government body, advocacy organization, data center developer, technology company, or utility. We accept no advertising or sponsorship from any party to these disputes.

Sourcing & accuracy

Content on this site summarizes third-party reporting, government documents, and published research; every substantive claim links to its source. We do not conduct original investigations. Summaries are our own words; the underlying reporting belongs to the credited outlets, and quotes belong to their speakers, presented with links to their original context. Information reflects sources reviewed as of the "updated" date in the site header. Statuses of projects, litigation, and legislation change quickly, and errors are possible — tell us if you spot one and we will review and correct it.

Neutrality of labels

Stance and status labels ("supports expansion," "opposes / restricts," "conditional / mixed," "rejected," and so on) are editorial shorthand based on officials' recorded actions and statements. They are simplifications of nuanced positions, not endorsements or criticisms. If you believe a label mischaracterizes a position, use the form above.

What this is not

Nothing on this site is legal, financial, or investment advice, and nothing here should be read as advocating for or against any specific project, vote, candidate, or piece of legislation. External links are provided for reference; we are not responsible for the content of linked sites, and linking does not imply endorsement. All trademarks and company names belong to their respective owners and are used only to identify the projects and parties involved.

Corrections

We publish corrections when we get something wrong. Use the tip & corrections form — anonymously if you like — and include a source where possible.